Contractor Walkthrough

Working with Edo State on EdoBuild 360°

Everything a construction company needs to do on the platform, in the order you will actually do it — registering the company, getting your login, running an assigned project, claiming milestones, getting inspected, and clearing corrective actions before they cost you.

Who this is for

Registered & prospective state contractors

Where you sign in

edobuild360.com/login

What you need

RC number, State Government Registration ID, tax clearance, contact email & phone

Time to register

About 20 minutes, plus verification

This guide follows the order you will actually work in. Stages 01 to 03 happen once — registering the company, being verified, and getting your login working. Stages 04 to 09 are the working rhythm you repeat on every project, for as long as your company holds a contract with the State.

Screen paths are written as they appear in your browser, like /contractor/dashboard. Anything in a coloured box is a deadline, a cost, or a step people commonly get wrong — read those even if you skim the rest.

Stage 01

Register your construction company

You finish with A submitted registration sitting at pending, awaiting agency verification.

Registration is public — you do not need an account to start. Go to edobuild360.com/register/contractor, or open the Sign in / Register menu above and choose Register a construction company.

The form runs across four steps. You can move backwards and forwards, but the whole form is submitted at the end, so set aside a single sitting and have your company documents — including your State Government Registration ID — to hand before you begin.

  1. Company information
    Identity and contact details for the business. You give three separate identifiers here — your RC number (CAC), your State Government Registration ID, and optionally your TIN. The primary contact email you give here becomes your portal login, so use an address the company will keep and monitor.
    • Company / business name required
    • RC number required — as registered with the Corporate Affairs Commission
    • State Government Registration ID required — the ID issued when your company registered with the Edo State Government (not your RC number, and not your TIN)
    • Year of incorporation
    • Primary contact name required, and their designation
    • Phone number required — compliance alerts are sent here by SMS
    • Email address required — this becomes your username
    • Physical address and LGA required. State is fixed to Edo.
  2. Directors
    Add at least one director exactly as registered with the CAC. Each entry takes a full name, a phone number and an optional NIN. Use Add director for additional names.
  3. Capacity and specialisation
    Tick every trade category you are competent to deliver — Building & Construction, Civil Engineering, Electrical Works, Mechanical Works, Roads & Bridges, Water & Sanitation, ICT & Digital, Furniture & Fittings, Landscaping, Plumbing. These categories are what the agency filters on when matching contractors to work.
    Then declare your maximum contract capacity in Naira and your permanent staff count, and upload your CAC certificate and tax clearance certificate (PDF, JPG or PNG).
  4. Declaration and consent
    Confirm the declaration of authenticity and give NDPR data-processing consent, then enter the authorised signatory's name, designation and the date. Both tick-boxes are mandatory — the form will not submit without them.
One company, one RC number If your RC number is already on the register you will see “A contractor with this RC number is already registered.” That means someone at your company has registered before. Do not create a second entry — use Forgot password on the login page with the original contact email, or ask the agency to point you at the existing record.

On submission you land on a confirmation page and your record is created with the status pending. Nothing else is required from you until the agency responds.

Stage 02

Verification and your Contractor ID

You finish with An active registration, a Contractor ID, and a portal account created against your contact email.

The Special Adviser's office reviews your submission. They check your CAC registration, your tax clearance and your insurance, and may schedule a site visit or a virtual verification before deciding. This step is entirely on the agency's side — there is nothing to chase in the platform while it runs.

When your company is approved, four things happen at once:

  1. Your registration goes active
    Status moves from pending to active. Only active contractors can be assigned to projects.
  2. You are issued a Contractor ID
    A permanent identifier in the form SA/CID/2026/0001. Quote it in all correspondence with the State — on claims, on correspondence about notices, and on tender documents.
  3. A portal account is created
    The account is created against your primary contact email, with the Contractor role and your company already linked to it.
  4. An approval email is sent
    It confirms the approval and carries your Contractor ID, with a link through to the login page.
Setting your password — read this before your first sign-in The approval email does not carry a password. Your account exists, but you set the password yourself: go to the login page, choose Forgot password, and enter your primary contact email. The reset link that arrives is valid for 60 minutes. This is the normal, expected route in — not a fault.
If you are declined or hear nothing Verification decisions are made off-platform. Use the live chat on any page, or the help centre, quoting your company name and RC number.
Stage 03

Your first sign-in and account set-up

You finish with A secured account, working notifications, and the platform installed on your phone.

  1. Set your password
    From the login pageForgot password → your primary contact email. Passwords must be at least 12 characters. Choose something long rather than something clever, and store it in your company password manager, not on a note by the site office.
  2. Sign in
    Enter your email and new password. You land on your company dashboard at /contractor/dashboard. A session lasts 8 hours before you are asked to sign in again.
  3. Turn on two-factor authentication
    Open the user menu (top right) → Security, at /account/security, and add an authenticator app. Two-factor authentication is optional for contractors and strongly recommended — this account can move money claims.
  4. Check your profile and notification preferences
    Under My profile and Notifications, confirm the email address and phone number on file. Compliance notices are sent by both email and SMS; a wrong number here is how cure deadlines get missed.
  5. Install it on your phone
    EdoBuild 360° installs as an app. On Android open the site in Chrome and choose Install app; on iPhone open it in Safari, tap Share, then Add to Home Screen.
    You get a bottom tab bar — Pay, Home, Plans, NCRs — plus an All sections sheet for everything else.
Guard this account If your company is ever blacklisted, every portal account tied to it is deactivated immediately and all your incomplete projects are flagged red. Equally, do not share one login across the site team — the platform records who submitted every claim and every response, and that audit trail is your evidence in a dispute.
Stage 04

Your workspace, screen by screen

You finish with A clear map of the places you will actually work, and what each one is for.

The sidebar only ever shows what your role can reach, so your menu is deliberately short. These are your screens:

ScreenWhereWhat you use it for
My Profile/contractor/dashboardCompany card, performance tier, your projects, recent claims, open notices
My Portal/portalScorecard, plan submissions, your NCRs, enforcement cases, licence & insurance expiry
Project Registry/projectsThe State project register; open any project for its full record
Building Plans/plansPlans you have submitted and their stage in the approval pipeline
Non-Conformance/ncrsNCRs raised against your work, with the corrective action and its due date
Payment claims/paymentsMilestone claims — submit new ones, track certification and payment
Fees & Payments/my/paymentsGovernment revenue invoices — pay them and download receipts
Reports/reportsGenerate your own performance report as PDF or CSV
Notifications/notifications/centreEvery alert raised against your company, in one place
Two screens reached from your dashboard, not the menu Compliance notices open from the red Open notices button on your dashboard, and New claim opens the claim form directly. Both live at /compliance and /payments/create if you prefer to bookmark them.
Stage 05

Managing an assigned project

You finish with A reliable weekly routine for reading the project's status the way the agency reads it.

You do not create projects. The agency registers each contract and assigns your company to it — at which point it appears under My Projects on your dashboard, and you can open its full record from the registry. Every project carries a reference in the form SA/PRJ/2026/001; use it whenever you contact the agency.

Four fields on the project record decide how the State sees your delivery:

FieldWhat it means for you
Health statusgreen on track · amber at risk · red in trouble. Set from inspections and open notices, not from your own reporting.
Physical completion %The verified figure. It is what a certifying officer will measure your milestone claim against.
Scheduled completionThe contract date. Overrunning it feeds the timeliness component of your performance score.
Stop-work flagIf active, work is legally halted and you cannot submit a payment claim until it is lifted.

A workable weekly routine

  1. Open your dashboard first
    It surfaces the three things that change: project health, the status of claims in flight, and the count of open compliance notices.
  2. Clear the notifications centre
    Anything raised against your company lands here — issued notices, corrective actions, claim decisions. Treat an unread badge as work.
  3. Check My Portal once a month
    It is the only place that warns you about insurance and tax clearance expiry. Documents show as OK, expiring within 60 days, expired, or missing a recorded date. Let insurance lapse and you put future awards at risk.
If you also submit building plans Your Contractor role can file plan applications at /plans/submit and track them at /plans. Each application gets a reference like EB/2026/00001 and moves through ten desks — Front Desk, Clearing House, Assessment, Payment, Accounts Audit, Vetting, Record, GM Decision, HC Signing, Archive. A plan can also be returned to applicant, which means it is waiting on you.
Stage 06

Submitting progress evidence

You finish with A milestone claim on record, an inspection automatically requested, and a reference to track.

On EdoBuild 360°, progress is evidenced through the milestone payment claim. Submitting one is how you tell the State that a stage of work is complete, and it is the event that triggers physical verification of what you have built. There is no separate “progress report” to file — the claim is the declaration, and the inspection is the proof.

  1. Open the claim form
    From your dashboard, + New Claim, or go to /payments/create.
  2. Choose the project
    The dropdown lists only projects assigned to your company that have no active stop-work order. If a project is missing from the list, that is why.
  3. Describe the milestone
    Give the milestone number (1, 2, 3 …) and a milestone name that matches the contract's wording, such as Substructure Completion. Vague names slow certification down.
  4. Enter the claimed amount and completion
    The amount in Naira, plus the claimed completion % the project has reached at this milestone. Claim the percentage you can defend on site — the certifying officer measures against what is actually built.
  5. Submit
    You get a reference in the form SA/PAY/2026/0001, the claim opens at pending inspection, and the Head of Inspections is notified that verification is required.
  6. Have the site ready
    Photographic and video evidence is captured by the inspector during the verification visit, not uploaded by you. Make sure the works are accessible, safe, and that someone who knows the job is on site.

How a claim travels

pending inspection certified paid

Track it at /payments, or open the claim itself to see the certified amount alongside what you claimed. The certified amount can be lower than the claimed amount — that is the inspection doing its job. Claims that look irregular against measured progress are flagged as anomalies and reviewed before payment.

Two things that will block a claim An active stop-work order on the project (the claim is refused outright), and a payment hold attached to an unresolved compliance notice. Clear the notice first — see Stage 08.
Stage 07

Getting a site inspection

You finish with A correct understanding of how inspections are triggered — and how to get one when you need it.

Inspections are conducted by state field inspectors and scheduled by the Head of Inspections. Contractors do not book inspection slots directly in the platform, and there is no “request inspection” button on your screens. Instead, three events bring an inspector to your site:

  1. You submit a milestone claim
    This is the main route, and the one you control. The claim raises a verification request the moment it is submitted (Stage 06). If you need an inspection, submit the milestone.
  2. A statutory phase falls due
    On projects running under building-control approval, the agency drives the statutory inspection phases — setting out, foundation, each structural floor, and so on — against the approved plan. You are notified when a phase is signed off or failed.
  3. A re-inspection is scheduled after corrective work
    When you have completed the corrective action on an NCR, the agency schedules the re-inspection and sets its date. Tell them the work is done — they cannot schedule what they do not know about.
To ask for an inspection outside those three Use the live chat on any page, or the help centre, quoting your project reference (SA/PRJ/…) and what is ready to be seen. Requests made this way are handled by the agency's support desk and passed to the inspections team.
What the inspector records A rating for the work, photographs and video from the site, GPS-stamped location, and any defects found. Those ratings feed 30% of your performance score, so treat the visit as part of the job, not an interruption to it.
Stage 08

Responding to corrective actions

You finish with Notices answered inside the cure period, NCRs cleared, and no escalation on your record.

The State has three separate instruments for putting things right, and they behave differently. Knowing which one you are looking at tells you what you can do about it.

Compliance notices — you respond in the platform

A compliance notice is a formal instruction, referenced SA/CN/2026/0001. When one is issued you receive an email and an SMS, both carrying the cure deadline. The standard cure period is 14 days, and the agency can set anything from 1 to 90. Every notice carries a severity of low, medium, high or critical, and names one of seven breach types:

Notice typeWhat it covers
WHS violationHealth and safety failures on site — unsafe scaffolding, missing PPE, unprotected excavations
Quality defectWork that does not meet the specification or the approved drawings
Time overrunProgramme slippage against the contract schedule
Financial irregularityDiscrepancies between what is claimed and what is verified on site
Site abandonmentThe site left unmanned, or works halted without agreement
Environmental breachDrainage, waste, noise or site-runoff failures
General non-complianceAny other breach of the contract or the building regulations

The notice lifecycle — you act at the highlighted step:

draft awaiting approval issued response received in cure period resolved

Miss it and the notice moves to escalated instead.

  1. Open the notice
    Click Open notices on your dashboard, or go to /compliance. Notices are grouped by status, most severe and soonest-expiring first.
  2. Read the violation and the required action
    Every notice states the violation, the specific action required of you, and the cure deadline. Do the work first — a response without remediation behind it simply comes back.
  3. Submit your response
    Use the Submit Response button and describe the remedial action taken. The form needs a real account of the work — at minimum 20 characters, but write it as a statement you would be content to see quoted back to you. Say what was done, when, and by whom.
    The button only appears while the notice is issued. Once you have responded, the notice moves to response received and the Head of Inspections reviews it.
  4. Keep your site evidence
    The response itself is written. Hold your photographs and delivery notes for the verification visit — that is where they are examined.
What missing the deadline costs When the cure deadline passes without a satisfactory resolution, the notice escalates automatically and the Special Adviser is notified. A critical notice can trigger a stop-work order — which halts the site and blocks every payment claim on the project — and a payment hold that is only released when the notice is resolved. Each open notice also costs you 10 points of performance score, each critical notice 20, and each stop-work 30.

Non-conformance reports — you fix, the agency closes

An NCR, referenced SA/NCR/2026/0001, records a specific defect found during inspection, at minor, major or critical severity. You can see every NCR raised against your company at /ncrs and on My Portal — but closing one is the agency's action, not yours.

open corrective action re-inspection closed
  1. You are told by SMS
    When a corrective action is assigned to your company, an SMS goes to your primary contact number with the NCR reference and the due date.
  2. Read the corrective action and its due date
    Open the NCR at /ncrs. It carries the defect, the required corrective action, the due date, and — once set — the re-inspection date.
  3. Do the work, then tell the agency
    There is no “mark as done” button for contractors. Report completion through the live chat or the help centre, quoting the NCR reference, so a re-inspection can be scheduled.
  4. The agency verifies and closes it
    After re-inspection the NCR is closed, or waived if the defect is accepted. Only then does it stop counting as open against your record.

Enforcement cases — read-only, and serious

Enforcement actions — stop-work, sealing, demolition flag, revocation, suspension — are listed on My Portal so you can see what is live against your projects. You cannot act on them in the platform. An appeal is lodged through the agency: contact the support desk with the case reference and your grounds, in writing, without delay.

Stage 09

Fees, your performance score, and getting help

You finish with Fees settled, a score you understand and can move, and a support route that works.

Paying government fees

Statutory fees — plan approval, inspection, certificate and penalty fees — are invoiced to you and paid through the Edo State revenue gateway. Open Fees & Payments at /my/payments, which shows what is outstanding across your account. Open an invoice, press Pay, complete the checkout, and the receipt is available from the invoice as soon as payment confirms.

Keep these separate in your head from milestone claims at /payments: fees are money you owe the State, claims are money the State owes you.

How your performance score is calculated

Every registered contractor carries a score out of 100 and a tier. It is published on the public contractor league table, and it is what the State looks at when awarding work. Four components, weighted:

ComponentWeightHow you move it
Completion rate30%Contracts completed against contracts awarded — finish what you start
Inspection quality30%The average rating across inspections on your projects
Compliance25%Starts at 100 and loses 10 per open notice, 20 per critical notice, 30 per stop-work
Timeliness15%Delivery against scheduled completion dates
TierScoreStanding
A80 – 100Preferred — strongest position for new awards
B65 – 79Good standing
C50 – 64Acceptable, with visible weaknesses
D35 – 49Under scrutiny
FBelow 35At risk of exclusion

Your current score and tier sit on your dashboard and on My Portal. For the full picture, go to /reports and generate My Performance Report as PDF or CSV — your portfolio, ratings and score history in one document.

Getting support

  1. Live chat — fastest
    The shield button at the bottom-right of every page, signed in or not. It answers platform questions immediately and can hand you to a human agent when you need one.
  2. Help centre
    Searchable guides at edobuild360.com/help, open to everyone, no login needed.
  3. Notifications centre
    /notifications/centre — the audit trail of everything the platform has told you, when chasing what happened to a claim or a notice.
Always quote a reference Contractor ID SA/CID/…, project SA/PRJ/…, claim SA/PAY/…, notice SA/CN/…, NCR SA/NCR/…, plan EB/…. A reference turns a support conversation into a resolution.
Quick reference

Keep this to hand

Reference formats

RecordLooks likeIssued when
Contractor IDSA/CID/2026/0001Your company is verified
ProjectSA/PRJ/2026/001The agency registers the contract
Payment claimSA/PAY/2026/0001You submit a milestone claim
Compliance noticeSA/CN/2026/0001A notice is drafted against you
Non-conformanceSA/NCR/2026/0001An inspector records a defect
InspectionSA/INS/2026/0001An inspection is conducted
Building planEB/2026/00001You submit a plan application

When something does not work

What you seeWhat to do
“A contractor with this RC number is already registered”Your company is on the register already. Use Forgot password with the original contact email rather than registering again.
“A contractor with this state registration ID is already registered”The same thing, caught on the other identifier — the company is already registered under that State Government Registration ID. Recover the existing account instead of creating a second one.
Approved, but no password anywhereExpected. Set it yourself: loginForgot password → your primary contact email. The link lasts 60 minutes.
Reset link says it has expiredLinks are valid for 60 minutes and single-use. Request a fresh one.
Your dashboard says no company is linkedThe account is not attached to a contractor record. Contact support with your Contractor ID — do not register the company a second time.
A project is missing from the claim dropdownEither it is not assigned to your company, or it has an active stop-work order. Check the project's record.
“Cannot submit claim: stop-work order is active”Resolve the underlying compliance notice first. The claim will go through once the order is lifted.
No Submit Response button on a noticeResponses are only accepted while the notice is issued. If it has already escalated, contact the agency directly.
An NCR is done but still shows openOnly the agency closes NCRs, after re-inspection. Report the completed work with the NCR reference so it can be scheduled.
A screen refuses you accessCorrect behaviour — your role reaches the screens listed in Stage 04. Anything else is staff-only.

Ready to get started?

Register your construction company to receive project opportunity notifications, track your performance score in real time, and demonstrate accountability to the Edo State Government.